Brent$97.57(≈RM398)▼ -5.87%WTI$89.92(≈RM367)▼ -1.51%Nat Gas$3.00(≈RM12)—Bunker$865.50(≈RM3,530)—Tapis$86.75(≈RM354)—JKM LNG$25.74(≈RM105)▲ +1.22%MGO$1289.50(≈RM5,259)—EU Carbon€85.09(≈RM394)▼ -1.00%TTF Gas€72.20(≈RM334)▲ +0.17%Diesel$4.87(≈RM20)▼ -4.70%Coal$146.25(≈RM596)▲ +0.97%USD/MYR4.0780—US Rigs551▲ +7 M/MRON95RM4.52(≈US$1.11)▼ -1.09% W/WRON97RM5.00(≈US$1.23)▼ -0.99% W/WDieselRM5.27(≈US$1.29)▼ -2.77% W/W
08:10 MYT
CommoditiesLife-SavingFirefightingManpowerPaintingDormitoryUAV TrainingConsultancy

Black Sea Mega-project Narrows First Gas Window to Early 2027 With Work in Final Execution Stage

Republished from Offshore Energy ·

Oil tanker sailing in the open sea at dawn

September 29, 2026 · 1 day ago

Positioned to bolster Europe’s energy security, a multibillion-euro gas project is rapidly advancing toward its launch.

OMV Petrom, Southeastern Europe’s integrated energy player, and Romgaz, Romania’s largest producer and main supplier of natural gas, have confirmed that the first gas from the Black Sea project is expected in the first half of 2027, following the offshore installation of a production platform and the completion of seven development wells.

The two joint titleholders of the Neptun Deep block have shed light on the project’s start-up timeline, highlighting that first gas production is anticipated to enter the National Transmission System (NTS) in the first half of 2027.

Christina Verchere, CEO of OMV Petrom, commented: “Narrowing the first gas window marks a major milestone for Neptun Deep and brings us closer to production.

“The project will play an important role in strengthening Romania’s energy security and positioning the country as a leading gas producer in the European Union. As we move towards first gas, our focus remains on safe, efficient and reliable execution.”

Given the recent offshore installation of the Neptun Alpha shallow-water production platform and the progress that has been achieved, OMV Petrom and Romgaz emphasize that the project remains on track.

After first gas reaches the entry point NTS, the project will transition into a gradual ramp-up and operational performance testing phase, with the production plateau expected to be reached by the end of Q3 2027.

Cristian Hubati, Member of OMV Petrom Executive Board, responsible for Exploration and Production, said: “We are entering the final stages of execution. Drilling operations continue, and we are approaching the completion of key infrastructure, including the offshore pipeline and the Natural Gas Measuring Station.

“Once installed, all systems and facilities will be subject to comprehensive inspection, testing and commissioning before start-up. Safety and operational readiness will guide every step as we prepare to deliver first gas from one of the most important gas projects in European Union.”

Republished from Offshore Energy.

View the original at Offshore Energy →

Source: Offshore Energy