Port Everglades Is Planning Its Growth in Cruise Operations

Port Everglades has set out a 20-year plan for its cruise business worth $1.7 billion, after a third consecutive record year.

By MarineCraft News Desk · Original report: The Maritime Executive ·

Cargo Ship with stacks of containers arriving at a port of call

Port Everglades has set out a 20-year plan for its cruise business worth $1.7 billion, after a third consecutive record year.

The Broward County port handled more than 5.38 million cruise guests in fiscal 2026, already ahead of a plan whose mid-case projection is 5.8 million by 2045 against a high case of 6.9 million. Nine cruise lines will homeport there in the 2027 season alongside a daily ferry service to the Bahamas. The port has created a separate cruise services division to manage the growth, headed by newly appointed director Martin Jackson, covering daily operations at its eight terminals and coordination with the lines.

Deputy Port Director Glenn Wiltshire said the port refreshes its master vision plan every five years across its cruise, bulk, breakbulk, container and energy business lines, and that the last update identified the $1.7 billion of cruise-related projects.

Most of the spending addresses an inheritance. The port opened in 1928 as one of Florida's first deep-water ports, and with one exception its eight cruise terminals began life as cargo sheds. Every terminal but Terminal 29 has been upgraded, and the port is working with Royal Caribbean on renovating and expanding that one with a parking garage, the nearest-term project. Terminal 18 is scheduled for the 10 to 20-year window, Terminal 19 needs refreshing, Terminal 21 is back under discussion with Carnival in the six to ten-year window, and Terminal 26, used primarily by Holland America and last worked on 12 years ago, falls in the 10 to 20-year window.

Bulkheads come with the terminals. Upgrades to berths 16, 17 and 18 have federal funding and will be done in 2029, timed around Royal Caribbean's use of the only berth that takes Oasis and Icon class ships. Shore power is planned for all eight terminals across the 20 years, with two federal grants secured and design under way for Terminal 25. The port is working with Florida Power and Light on a substation capable of powering eight cruise ships at once. Parking is the fourth investment category, driven by shorter cruises bringing more passengers who drive.

The sequencing is the transferable lesson. Shore power at a cruise berth is a grid project before it is a quayside one, and Port Everglades is building a substation to serve it. Malaysian ports weighing shore power for cruise or container berths face the same order of dependency, and the civil works are the easy part.

This brief was written by the MarineCraft News Desk from the source’s reporting. Read the original coverage at the source.